Essential refurbishment work on the roof of the L Building will begin this winter quarter. Please be aware of additional noise in the area from Monday, Jan. 13, to Friday, Jan. 17, between approximately 7–9 AM due to construction activity.
More Information:
Notice: L Building Roof Refurbishment
Much-needed refurbishment work on the roof of the L Building is scheduled to begin this winter quarter. The project includes replacing and repairing air handling units, skylights, and roofing.
Key Dates and Information:
- During early January, contractors will set up fencing for construction materials and equipment.
- Roof work, including some demolition, will commence the week of Jan. 13–17.
- Expect additional noise in the area between 7–9 AM. The noisiest work is scheduled for early mornings and should conclude by 8:30–9 AM to minimize disruptions during busy times.
The building and classrooms will remain accessible throughout the project. Further updates will be provided as work progresses. Thank you for your patience as we make these important improvements.